Airside Logistics New Facilities
(Quick Facts) | |
Project Name: | Airside Logistics New Facilities |
Project Location: | Mount Isa Airport Aviation Precinct |
Project Cost: | 1.8M |
Date of Completion: | October 2012 |
Duration: | 22 Weeks |
Project Scope:
Design and Construct of a freight forwarding facility located in Mount Isa and supply and service corridor and upgrade the fire ring mains of the terminal.
Project Challenges:
Remote area works involve a high level of pre-planning for the resource delivery and logistical time frames.
Project Delivery:
This project had a 1-month delay due to the late delivery of a specialized internal wall panel